Walker recycles!

Don't forget to save your plastic, your paper and your aluminum cans. There's now a recycling bin available 24/7 behind the Walker Municipal Building, 10136 Florida Boulevard.

Read more


Up & coming events

>>August 10
Public informational meeting on alcohol referendum


Our free newsletter

Keep up with all the latest happenings in the Town of Walker. Subscribe for free to The Walker Report, delivered right to your Inbox.

Subscribe

Archives


Follow us on
Facebook & Twitter

Join our nearly 800 fans on Facebook or our followers on Twitter. Browse through our photo albums and get up-to-the-minute updates on happenings in our hometown. Click the images below to start.

Town of Walker on Facebook Town of Walker on Twitter


Most popular pages

Click the images below to see what Walker is talking about.

 

 

For homeowners: Acquiring
residential construction permits


Permits & Inspections
Walker Municipal Building
10136 Florida Boulevard
Walker, LA 70785

Phone: 225.665.8893

Hours
7 a.m. to 5:30 p.m.
Monday through Thursday

Building permit application process

Homeowners must supply the following construction documents to the Town of Walker:

1. House plans
2. A plat showing the location of the house
3. A completed Building Permit application. To obtain one online, click here.
4. Notarized affidavit.

Once those materials have been submitted, the construction documents are in the plan-review stage. The Permit Department will calculate a building permit fee, review the plans for code compliance and generate a plan-review letter at the end of the review. You will be contacted and informed of the permit fee and any plan-review changes that must be made to meet code compliance.

Now that you have a permit

: : Permits must be posted on the job site, along with the address and lot number.
: : Electrical, plumbing and mechanical permits are required on all jobs before the rough-in begins.
: : Inspections of foundations [including rough-in plumbing] will be done as soon as possible after the call for an inspection.
: : If an elevation certificate is required, a copy must be supplied to this office before the final inspection.
: : All other inspections, such as electrical, plumbing and mechanical, will be done the same day or the next business working day.
: : No inspections will be done without a permit.
: : All jobs are required to have a dumpster for trash and construction debris removal.
: : No open burning.
: : All jobs are required to have a portable toilet on site.
: : Erosion protection shall be installed within the street right-of-way before construction begins.
: : A $50 re-inspection fee will be charged when a second trip to a construction site is required due to rejection or lock-out.

Order of inspections

1. Temporary electric pole
2. Rough-in plumbing
3. Foundation
4. Electrical rough in
5. Mechanical rough in
6. Plumbing top out/gas
7. Rough framing
8. Electrical final
9. Plumbing final
10. Mechanical final
11. Sewer tie-in
12. Final framing building [require top-of-floor elevation certificate; issue occupancy certificate]